Home » Portfolio » Healthcare » Royal Hallamshire Hospital

Royal Hallamshire Hospital

The project was for the internal strip out and refurbishment of wards in the Royal Hallamshire Hospital, Sheffield.

The works included the revamp and expansion of the Haematology Wards O1, O2, P3 and P4, including the Haematology Clinic, and the construction of a new Bone Marrow Transplant Unit.

Logistically challenging and requiring an external lift covering two floors, the contract was undertaken whilst the hospital remained in full 24 hour use. 

Close liaison with the hospital staff and medical teams ensured that disruption to every day running of the department was kept to a minimum for the duration of the 42 week contract.

Project: Haematology Unit

Location: Sheffield, South Yorkshire

Client: Sheffield Teaching Hospitals

Value: £ 2,400,000

Programme: 42 weeks

Architect: Race Cottam Associates

Contract: JCT 2005