Home » Portfolio » Healthcare » BMI Highfields Hospital

BMI Highfields Hospital

The project was for the extension to the existing operating theatre and extensions and remodelling of the wards.

The hospital remained open throughout the works, requiring close liaison between the site team and the staff to ensure we did not impact on their ability to provide healthcare services.

In order to facilitate the co-ordination of continued healthcare services and operations within the hospital, the contract was carried out in six distinct and separate phases, enabling each department to be kept in a sterile condition whilst the construction works was completed.

Project: BMI Highfields Hospital

Location: Rochdale, Lancashire

Client: BMI Healthcare

Value: £ 2,400,000

Programme: 69 weeks across six phases

Architect: James Totty Partnership

Contract: JCT 1998

picture
click images to view more »